Construction of an energy centre to supply the new brewery site in Munich, Langwied.

Installation of a multi-boiler system to supply heat to the production facilities. On-site electricity generation via two CHP modules and utilisation of waste heat for the heating network.

Technical data:

  • High-pressure hot water: 32 MW, 160 °C, 16 bar
  • Hot water: 16 MW, 105 °C, 10 bar
  • Central heating: 3 MW, 35 °C, 10 bar
     

 