AGO’s contract covered the detailed design, installation and commissioning, including trial operation, for the biomass combined heat and power plant in Wunsiedel. The main components of this plant are: combustion system, thermal oil boiler, ORC turbine, wood chip dryer, electrical engineering and process control system.

Technical data:

  • Heat output: 4,580 kW
  • Thermal oil boiler: 3,995 kW
  • ORC turbine: 758 kW
  • Heat input of wood chip dryer: max. 4,400 kW
  • Design: AGO