HUK Coburg

As part of the refurbishment and capacity upgrade to meet future cooling requirements, the existing cooling towers 4 and 5 were replaced with two new stainless steel cooling towers fitted with finned heat exchangers to prevent mist formation. The pipework, pumps and water treatment systems were upgraded.

Technical data:

  • New, higher cooling capacity: 2 × 1,570 kW
  • Electrical connected load: 2 × 42.8 kW
  • Cooling tower water flow rate: 2 × 272 m³/h
  • Cooling tower water treatment: approx. 2 × 3.5 m³/h
     

 

Similar projects

SÜC Coburg
Heat Power
BEKA Wannberg
Ventilation
Intercity Hotel Hamburg
Cooling Ventilation