Gropper Dairy in Bissingen commissioned AGO GmbH to supply, deliver and install a turnkey electric steam boiler system with an electrical output of 5,500 kWel. 

The scope of supply included the electric boiler, the complete feedwater treatment system, the steam distribution system, the integrated pump modules, and all necessary pipework and auxiliary equipment. The new system was connected to the existing infrastructure via a pipe bridge provided by the client.

Technical data:

  • Electrical power (boiler): 5,500 kWel at 690 V
  • Steam output (rated load): 7,500 kg/h at 11 bar